Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

City of Nanaimo to hire private company to handle travel bookings

Mayor says decision to hire outside firm not related to misuse of travel expenses

Regional District of Nanaimo sees increase in building activity

Three-year rise in development permits exceeds provincial average

Nanaimo animal control says 300 dead rabbits recovered

Province of B.C. confirms more positive tests for rabbit haemorrhagic disease

Nanaimo company awarded $33-million Site C contract

F&M Installations Ltd. will build substation for B.C. Hydro megaproject

NRE says some form of shutdown now unavoidable

City of Nanaimo staff has been asked to look into options to support $6-million recycling depot

Celebrating our transit drivers on their day

March 18 is International Transit Driver Appreciation Day

Transport Canada will review all port authorities, including Nanaimo’s

Series of meetings and round tables could lead to revamping port authorities’ business models

Nanaimo fire trucks rolling out more often than ever

Fire chief projects that Nanaimo Fire Rescue will answer 10,000 callouts in 2018

B.C. cyclist races to first win of the season in New Zealand

Casey Brown captures Enduro title by more than two minutes at Crankworx Rotorua

Notorious Russian troll farm also took swipes at Canadian targets

Targets included oil infrastructure and Prime Minister Justin Trudeau.

VIDEO: Release and catch at Colliery Dam Park

Trout released at lower Colliery dam in Nanaimo

Cirque du Soleil aerialist dies after fall during Florida show

Longtime performer fell while performing in VOLTA

Canada earns second Paralympic Games silver in 20 years

Held 1-0 lead in para hockey game from 12:06 of first to dying seconds of third and lost in overtime

LETTERS: Two views of oil pipeline protests

U.S. and other petroleum-rich countries aren’t cutting production

Most Read