New dike makes breach safe, allows downstream work on sumps to prevent further tailings to escape as mine investigation continues

An upstream dike has been completed at Mount Polley Mine, allowing investigators to probe the site of the original Aug. 4 dam breach.

The new structure is to make the breach area safe for inspection and work below, not to repair the original breach or retain water in the tailings pond, said Steve Robertson, Imperial Metals vice-president for corporate affairs.

“We’ve finished construction of the upstream dike, and now we’re establishing the sumps on the upstream side of that, and that will intercept the water that’s going to continue to flow out of the tailings,” Robertson said in an interview Friday. “If anything should get past that, we’ll have another sump outside of the breach that will capture any water that comes out through the breach and make sure that it gets put into the reclaim system.”

The sumps act as settling ponds, with the water pumped back up to another pit on the site of the copper-gold mine near Williams Lake.

Robertson said the continued work addresses the Ministry of Environment‘s non-compliance notice issued to the company Sept. 9, regarding discharge of water into the Hazeltine Creek channel.

Most of the available mine employees are back at work, with about 30 working on cleanup around Quesnel Lake. Work is expected to continue until there is too much snow cover to continue.

The environment ministry released more water test results Thursday, showing water collected at various sites and depths in the area remains safe to drink.

The immediate area of the tailings spill remains a “do not use” zone, and Interior Health advises local residents to avoid drinking cloudy water.

 

Just Posted

New COVID-19 cases on Vancouver Island by local health area for the week of June 6-12. (B.C. Centre for Disease Control image)
New COVID-19 cases up on Island, but health officials say trends going right way

There were 22 new COVID-19 cases in Greater Victoria last week after just four the week before

Regional District of Nanaimo is looking to repair sewage pipe in the Hammond Bay Road area, which was corroded by gas. (Black Press file)
Corroded sewer pipe along Nanaimo’s Hammond Bay Road will cost $5.5 million to fix

Pipe replacement and reinforcement part of $6.9-million infrastructure project

Kimberly Bussiere and other laid-off employees of Casino Nanaimo have launched a class-action lawsuit against the Great Canadian Gaming Corporation. (Chris Bush/News Bulletin)
Laid-off Casino Nanaimo workers launch class-action lawsuit against corporation

Notice of civil claim filed on April 6 at Supreme Court of B.C. in Nanaimo

Beban Pool is expected to re-open Oct. 4 after a vote by councillors at a finance and audit committee meeting Wednesday, June 16. (News Bulletin file photo)
City of Nanaimo will re-open Beban Pool in October

User groups warn COVID-19 pool closures have left a gap in water safety education

People line up to get their COVID-19 vaccine at a vaccination centre, Thursday, June 10, 2021 in Montreal. THE CANADIAN PRESS/Ryan Remiorz
Vaccines, low COVID case counts increase Father’s Day hope, but risk is still there

Expert says people will have to do their own risk calculus before popping in on Papa

FILE – A science class at L.A. Matheson Secondary in Surrey, B.C. on March 12, 2021. (Lauren Collins/Surrey Now Leader)
Teachers’ union wants more COVID transmission data as B.C. prepares for back-to-school

BCTF says that details will be important as province works on plan for September

Provincial health officer Dr. Bonnie Henry outlines B.C.’s COVID-19 restart plan, May 25, 2021, including larger gatherings and a possible easing of mandatory masks on July 1. (B.C. government photo)
B.C. records 120 new COVID-19 cases, second vaccines accelerating

Lower Pfizer deliveries for early July, Moderna shipments up

A Heffley Creek peacock caught not one - but two - lifts on a logging truck this month. (Photo submitted)
Heffley Creek-area peacock hops logging trucks in search of love

Peacock hitched two lifts in the past month

The Calgary skyline is seen on Friday, Sept. 15, 2017. THE CANADIAN PRESS/Jeff McIntosh
2 deaths from COVID-19 Delta variant in Alberta, 1 patient was fully immunized

Kerry Williamson with Alberta Health Services says the patients likely acquired the virus in the hospital

B.C. Public Safety Minister Mike Farnworth and Attorney General David Eby attend opening of the first government-run B.C. Cannabis Store, Kamloops, Oct. 19, 2018. (B.C. government)
B.C. government to allow home cannabis delivery starting July 15

Added convenience expected to persuade buyers to ‘go legal’

The first suspension bridge is the tallest in Canada, with a second suspension bridge just below it. The two are connected by a trail that’s just over 1 km. (Claire Palmer photo)
PHOTOS: The highest suspension bridges in Canada just opened in B.C.

The Skybridge in Golden allows visitors to take in views standing at 130 and 80 metres

BC Green Party leader and Cowichan Valley MLA Sonia Furstenau introduced a petition to the provincial legislature on Thursday calling for the end of old-growth logging in the province. (File photo)
BC Green leader Furstenau introduces old-growth logging petition

Party calls for the end of old-growth logging as protests in Fairy Creek continue

B.C. Premier John Horgan leaves his office for a news conference in the legislature rose garden, June 3, 2020. (B.C. government photo)
B.C. premier roasted for office budget, taxing COVID-19 benefits

Youth addiction law that triggered election hasn’t appeared

Most Read