Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Suspended Snuneymuxw chief issues statement on suspension

John Wesley denies wrongdoing and said suspension is invalid under First Nation council rules.

Nanaimo RCMP warn of NAC and Beban Park pool thefts

Nanaimo RCMP warning of increase in locker room thefts at public pool complexes.

Nanaimo’s child poverty rate rose to 24.6 per cent in 2016 says report

The 2017 State of the Child report was released Friday

Snuneymuxw chief still in running for leadership

Statement expected today from suspended Snuneymuxw Chief John Wesley

UPDATE: Suspect charged after stabbing at Nanaimo motel

Assault among charges against woman, who sees next day in court Tuesday, Nov. 21.

100,000 bulbs shine bright for Lights of Hope

St. Paul’s Hospital in Vancouver launched its annual campaign to raise funds for equipment, research

‘I will now live in consistent fear’: Allan Schoenborn granted escorted leaves

The Merritt man was deemed not criminally responsible in the killing of his three children in 2008

Beefs & Bouquets, Nov. 16

To submit a beef or a bouquet to the Nanaimo News Bulletin, e-mail bulletinboard@nanaimobulletin.com

Hammy the deer dodges conservation officers in Prince Rupert

The famous Prince Rupert hammock deer maintains his purple threads

‘No shirt, no service, no Canada’

Shirtless Tacoma man arrested after Canadian border officials say they found meth in rental vehicle

Nasty note on B.C. windshield sparks online outrage

Vernon’s Bailey McDonald is using a painful experience to start conversation about invisible illness

Port Alberni resident robbed with weapon, thieves steal thousands

Most of the stolen currency is in Canadian $100 bills. The police investigation is ongoing.

VIDEO: Great Nanaimo Toy Drive kicks off 2017 campaign

Toys can be donated at various locations throughout Nanaimo until Dec. 16

Federal funding to combat guns, gangs and opioid crisis

Public Safety Minister Ralph Goodale said illicit drugs are often main cause of guns, gangs violence

Most Read